05-27-2020.CLUBHOUSE RENOVATION SUBCOMMITTEE BACKUP

FRENCHMAN’S CREEK- PRICING REVISED

Alterations primarily inside the Envelope

01 14 19 11 05 19

EXTERIOR WORK

A- Envelope

a. Replace exterior windows to impact windows per sketches b. Paint Exterior of Building c. Seal all eave vents – replace/repair eaves to remove the vents d. Fix/repair all gutters e. New pavers at drop off f. Caulk all windows and seal existing windows to remain

B- Roof

a. Replace all roof tile b. Repair all plywood damaged c. Alternate to remove center roof trussed and replace with new trusses for space to meet code for AC units d. Remove pop up ceiling over library room and repair roof and repair sagging ceiling with structure. e. All roof areas to have icynene

C- Porte-Cachere

a. Replace ceiling and lighting b. Add new sconces at drive through

D- Walkway Covered at Porte Cachere a. New walkway with columns b. New roof and parapet wall

E- Mechanical

a. Move chiller units from roof to tennis court area b. Add 2 new Outside Air Units in place of chillers on roof

F- Storage Room over cart barn a. Add 2 nd floor wall and new roof to connect to main roof for increased storage b. Add columns on West side of cart barn and extend new floor to increase storage area above c. Rework entry into storage room for a level entry d. New doors and entry