ClubhouseConstructionResport-ISSUE-9

JANUARY MILESTONES

1

3

2

4

5

1

Complete construction of upper level CMU walls. Complete construction of upper level columns. Continue installation of upper level precast joists. Begin pour for roof slab. Pour Loading Dock slab (on grade).

2 3 4 5

Created on 01/18/23