05-27-2020.CLUBHOUSE RENOVATION SUBCOMMITTEE BACKUP
TIMELINE
WEDNESDAY, APRIL 17, 2019
Vote by the Membership at a 2:30 p.m. Special Meeting.
Contracts with Architects, Owners Representative, Decorator and Construction Auditor Negotiated and signed.
MAY 2019
Focus Groups with the Architect and Decorator conducted to allow member input into final plans.
FALL OF 2019
Architect prepares final plans and construction drawings; needed permits and site plan approval obtained from the City of Palm Beach Gardens and general contractor hired.
JUNE 2019 TO APRIL 15, 2020
Construction begins—expected to be completed in 12 to 14 months.
APRIL 15, 2020