Clubhouse Construction Report Issue 3 July 2023

MILESTONE #1

Completed south retaining wall, and 90% of east and west retaining walls on the north side of the construction site.

MILESTONE #2

Waterproofing elevator pits (ongoing).

MILESTONE #3

Continue working on foundation.

MILESTONE #4

Begin construction of Concrete Masonry Unit (CMU) walls.

UPCOMING MILESTONES

4

4

1

5

3

7

2

6

1 2 3 4 5 6 7

Complete waterproofing for elevator pits. Finish retaining wall west section. Continue building Concrete Masonry Unit walls. Install drainage structure on south side. Complete building foundation. Commence site work at the Porte Cochére ramp. Complete retaining wall east section.