CLUB BUILDING PROJECT PACKET[1]

TIMELINE

WEDNESDAY, APRIL 17, 2019

Vote by the Membership at a 2:30 p.m. Special Meeting.

Contracts with Architects, Owners Representative, Decorator and Construction Auditor Negotiated and signed.

MAY 2019

Focus Groups with the Architect and Decorator conducted to allow member input into final plans.

FALL OF 2019

Architect prepares final plans and construction drawings; needed permits and site plan approval obtained from the City of Palm Beach Gardens and general contractor hired.

JUNE 2019 TO APRIL 15, 2020

Construction begins—expected to be completed in 12 to 14 months.

APRIL 15, 2020

Club Building Project - April 2019 17

17/22